Skip to content

20 & 40 ft · 4–25 m³/h · factory tested

Containerized Water Treatment Plant — Turnkey Systems in 20 and 40 ft Containers

Quick answer

A containerized water treatment plant puts pretreatment, reverse osmosis, disinfection, controls and lighting inside a 20- or 40-foot container. Capacities run from 4 to 25 m³/h. The unit is assembled and wet-tested in the factory, then shipped, set on a foundation and connected to water, drain and power. Turnkey scope covers design, manufacturing, shipping, installation, commissioning and training.

Green containerized water treatment plant with access doors open
A containerized plant arrives as one unit; site work is limited to foundation and connections.
Permeate per container
4–25 m³/h Permeate per container
Container sizes
20 / 40 ft Container sizes
Installed motor power
7–30 kW Installed motor power
RO recovery
55–75% RO recovery
Reviewed by HydroWorks Engineering Team Updated

01

What is a containerized water treatment plant?

A containerized plant is a complete treatment train built inside a steel ISO container. Depending on the water analysis, it can hold multimedia filters, softeners, dosing stations, reverse osmosis, UV or ozone, a control panel, lighting, ventilation and drains. The container protects the equipment from weather and unauthorised access, and provides a stable base that can be lifted onto a prepared foundation. The plant arrives as one transportable unit rather than as loose vessels and pipework.

The difference from a skid is the enclosure, not the process. A skid assumes a plant room with walls, lighting, drainage and ventilation; a container supplies all four. That makes the container the usual choice when civil works are slow, the site is remote, or the plant may be relocated later. Where a suitable building already exists, a skid is usually the simpler and more economical option.

The container itself is part of the equipment. Walls and roof are insulated, the floor has a drain, and ventilation maintains a working temperature for pumps, membranes and electronics. Cable trays, service lighting and a lockable door are fitted during fabrication, so the site does not need to build a plant room. Raw water tanks, treated water storage and large chemical tanks usually remain outside because they do not fit or are better placed at ground level.

  • 20-foot container for compact trains and lower flows
  • 40-foot container for higher flows or more process steps
  • ISO corner castings for lifting and securing on the ship
  • Lockable access doors, service lighting and a cable tray

02

Which capacity and container size fit your site?

Containerized RO systems are built from 4 to 25 m³/h. A 20-foot container usually carries 4–10 m³/h with pretreatment; a 40-foot container carries 10–25 m³/h or a smaller flow with more treatment steps, such as softening, carbon, RO and a clean-in-place unit. Capacity is set by peak demand and daily volume, not by the container size alone, and the layout is confirmed on a general arrangement drawing before fabrication.

Containerized RO plant models
ModelPermeate (m³/h)Motor (kW)RecoveryContainer
CK-RO-4000L4755–60%20 ft
CK-RO-5000L5855–65%20 ft
CK-RO-10T101860–70%20 or 40 ft
CK-RO-20T203065–75%40 ft
CK-RO-25T253065–75%40 ft

Permeate rated at 25 °C. Recovery depends on feed TDS, temperature and pretreatment; motor ratings refer to the high-pressure pump.

03

What is included in a turnkey delivery?

Turnkey means one contract covers the plant from design to operator training. The boundary must be written into the quotation, because site work is always shared. The supplier normally provides engineering, fabrication, factory testing, packing, shipping documents, installation supervision, commissioning and training. The buyer normally provides a level foundation, power supply to the container, raw water connection, drain, treated-water storage and local permits.

Scope discipline matters most at the interfaces. The quotation should list who supplies the foundation, the power cable and breaker, the raw water pump, the drain, the treated-water tank and the local permits. It should also state what testing is done at the factory and what is repeated on site, and which party pays for standing time if utilities are not ready. A clear boundary prevents the most common commissioning dispute: equipment that is complete but cannot be started.

Turnkey delivery scope
StageSupplier scopeDeliverableBuyer scope
DesignWater analysis review, process design, layout, electrical and piping drawingsApproved drawing set and equipment listSite data, water analysis, utility limits
ManufacturingVessel fabrication, skid assembly, piping, wiring, panel buildingCompleted plant with nameplates and documentationApproval of submittals and change requests
Factory testingPressure test, electrical check, instrument calibration, wet testTest report, photos and inspection recordWitnessing if required by contract
ShippingPreservation, packing, lifting plan, export documentsContainer or flat rack ready for transportImport clearance, inland transport, site unloading
InstallationInstallation manual, remote support, or supervisor on sitePlant set, levelled and connectedFoundation, power cable, water and drain connections
CommissioningFlushing, membrane loading, pressure and recovery setting, water testCommissioning report and as-built notesFeed water, power, chemicals and drain available
TrainingOperator training on start-up, backwash, CIP and troubleshootingTraining record and operation manualOperators released from other duties

Scope is confirmed line by line in the quotation; anything not listed is excluded.

04

How is the plant tested before shipment?

Every containerized plant is assembled and tested as a unit before it is packed. Testing starts with a pressure test of vessels and piping, followed by an electrical inspection and instrument calibration. The plant is then run wet with feed water to check pump rotation, permeate flow, recovery, conductivity, leak points and every alarm and interlock. The test report, with readings and photographs, is issued before shipment.

The wet test uses the actual pretreatment and RO train, not a bypass. Where the customer cannot supply representative feed water, the test is run on prepared water of similar conductivity and the report states the substitution. Membranes are loaded for the test, then preserved for transport; instruments are zeroed and ranged before packing. Photographs of the internal layout, pipe labels and panel are included so the site team can compare on arrival.

  1. 01

    Pressure and leak test

    Vessels, headers and piping are tested above working pressure; flanges and welds are checked.

  2. 02

    Electrical and control check

    Panel wiring, motor rotation, instrument signals and safety interlocks are verified.

  3. 03

    Wet test

    The plant runs on feed water; permeate flow, recovery and conductivity are recorded.

  4. 04

    Alarm and interlock test

    Low pressure, high pressure, low level and conductivity alarms are triggered and checked.

  5. 05

    Preservation and packing

    Membranes are preserved, loose parts secured, openings sealed and the container prepared for sea freight.

05

Why choose containerized instead of a site-built plant room?

The choice is usually decided by site conditions rather than by process. A container shifts fabrication and testing into a factory, reduces site labour, and removes the need for a permanent building. That matters where the site is remote, the climate is harsh, the project schedule is short, or the plant may move to another location. A site-built plant room can be cheaper when a suitable building already exists and local contractors are available.

Containerized versus site-built plant room
FactorContainerizedSite-built plant room
Civil worksLevel foundation and cable trench onlyBuilding, drains, lighting, ventilation
ScheduleFactory build in parallel with site preparationCivil works precede equipment installation
Quality controlAssembled and tested under factory conditionsDepends on site supervision and weather
RelocationCan be lifted and moved as one unitEffectively permanent
ExpansionAdd a second container or extend the trainBuilding space and civil work required
Weather protectionInsulated, ventilated, lockable enclosureDesigned and built for the site

Both options use the same process equipment; the difference is where it is assembled and how it is protected.

06

Where are containerized plants typically used?

Containerized plants suit sites where a permanent building is impractical or slow to build. Typical uses include remote communities, construction and mining camps, island and coastal settlements, industrial parks, agricultural estates and temporary facilities. The feed water can be borehole, river, lake, municipal supply or seawater where a desalination train is included. The common thread is a need for potable or process water at a defined flow, with limited site labour.

Each site has a different constraint. A mining camp may need dust protection and high recovery because water is trucked in; an island community may need seawater desalination and corrosion protection; an industrial park may need process water at a constant conductivity. The container layout should be confirmed against these constraints rather than chosen from a standard size list.

  • Remote communities and worker camps
  • Island, coastal and off-grid sites
  • Industrial parks and factories without a plant room
  • Agricultural estates and livestock operations
  • Temporary or relocatable facilities

07

How are shipping, installation and commissioning handled?

A 20-foot container measures about 6.1 m long and a 40-foot container about 12.2 m; weight depends on the process train and must be confirmed on the packing list. The container is lifted by its corner castings, set on a level reinforced foundation, and anchored against wind. Site work then consists of connecting raw water, treated water, drain, power and any chemical dosing lines. Commissioning typically takes three to seven days, including flushing, membrane loading, set-point adjustment, a water test and operator training.

Shipping documents usually include the packing list, weight certificate, lifting points, electrical drawings and the factory test report. The container can travel as a standard ISO unit or on a flat rack if height is restricted. On arrival, inspect the corner castings, doors and visible pipework before lifting; note damage on the delivery receipt and photograph it. Installation supervision can be remote, but the first start-up should be witnessed by someone who can stop the plant if a reading is wrong.

  • Confirm foundation dimensions, loading and anchor points before delivery
  • Provide a power supply matched to the installed motor and control voltage
  • Keep the container accessible for membrane and filter replacement
  • Record commissioning readings as the baseline for later maintenance

08

Can a containerized plant work in hot, cold or coastal climates?

Yes, with the right enclosure options. Hot climates need ventilation, insulation and sometimes air conditioning to keep the control panel and membranes within temperature limits. Cold climates need insulation, heat tracing on exposed lines and freeze protection for standby equipment. Coastal sites need corrosion-resistant coatings and stainless or plastic wetted parts. Sand and dust require filters on ventilation openings and a maintenance schedule for cooling surfaces.

RO output falls as feed temperature drops; winter design should use the lowest expected water temperature, not the summer value.

Specifications

Delivery and service — typical ranges

Item Typical range
Standard skid lead time 15–30 days after drawing approval
Containerized / turnkey lead time 30–60 days after drawing approval
Warranty 12–18 months from shipment
Factory testing Hydrostatic pressure test and trial run with water before packing
Documentation General arrangement drawing, P&ID, test record, O&M manual and spare-parts list
Packaging Seaworthy plywood crate, or container for containerized plants
Installation support Remote guidance as standard; on-site engineer available on request
Operator training 1–2 days at commissioning, covering operation, CIP and consumables
Spare parts Recommended two-year list quoted separately with the equipment
Payment terms Typically 30% deposit and 70% before shipment; confirmed in the quotation
Minimum order 1 unit
Loading port Guangzhou or Shenzhen, China
Power supply 220/380/415/440 V, 50/60 Hz; confirmed on order
Ambient temperature 5–40 °C
Enclosure protection IP54 for indoor skids; higher IP available on request
Certification CE and ISO 9001; model-specific test reports on request

Typical industry ranges for planning. Final scope, commercial terms and lead time are confirmed in the quotation.

FAQ

Frequently asked questions

Questions buyers actually ask during sizing and quotation. Answers match the specifications above.

01 What capacity range is available in a container?
The containerized RO range covers 4–25 m³/h with models from CK-RO-4000L to CK-RO-25T. A 20-foot container usually handles 4–10 m³/h; a 40-foot container handles 10–25 m³/h or a lower flow with more pretreatment. Larger flows are met by combining containers or using a site-built plant.
02 What is the difference between containerized and skid-mounted?
The process equipment can be identical. A skid needs a plant room with walls, lighting, drainage and ventilation; a container provides them and can be relocated as one unit. Choose a container for remote or temporary sites; choose a skid when a suitable building already exists and capital cost is the priority.
03 Can a containerized plant treat borehole, river or seawater?
Yes, but the process train changes. Borehole water may need oxidation, filtration and softening before RO; river water usually needs coagulation, multimedia filtration and disinfection; seawater needs a seawater RO membrane array with higher pressure and material ratings. The container size follows the train, not the other way round.
04 Does the container include pretreatment and disinfection?
It can. Multimedia filters, softeners, dosing stations, cartridge filters, UV or ozone and a clean-in-place unit can all be mounted inside, subject to space. The general arrangement drawing shows exactly what is inside and what is installed separately, such as raw water tanks or treated water storage.
05 Does a containerized plant need a concrete foundation?
Yes. It needs a level, reinforced foundation rated for the operating weight, with anchor points at the corner castings and a cable trench or duct. A simple slab may be enough on stable ground, but the design must be confirmed by a local structural engineer and by the container loading data.
06 How long does installation and commissioning take?
Mechanical and electrical connections usually take a few days after the container is set and utilities are available. Commissioning typically takes three to seven days: flushing, membrane loading, pressure and recovery adjustment, water testing and operator training. Delays usually come from missing power, water or drainage, not from the plant itself.
07 Can it operate in cold or hot climates?
With the right options, yes. Cold climates need insulation, heat tracing and freeze protection, and the design should use the lowest expected feed temperature because RO output falls with temperature. Hot climates need ventilation, insulation and possibly air conditioning for the control panel. Coastal sites need corrosion protection.
08 What warranty and support are included?
Equipment is covered by a 12–18 month warranty against manufacturing defects, confirmed in the contract. Support includes operation and maintenance manuals, commissioning, operator training and remote troubleshooting. Spare parts recommendations and consumable lists are provided so the plant can be maintained locally.
09 How much does a containerized water treatment plant cost?
Cost depends on permeate flow, raw water quality, pretreatment, membrane and pump selection, container size, insulation and control level, plus freight and site scope. A 4 m³/h brackish-water unit and a 25 m³/h seawater unit are not comparable. Provide the water analysis and site conditions for an itemised quotation.

Next step

Send your water analysis, get a factory quotation

Tell us the source water, TDS, hardness, iron and daily demand. Factory engineers reply with a flow rate, process train and budget range within one working day.